Energy Transition Roadmap

Solomon Islands Energy Sector & Capacity Expansion Project

98%
Diesel Dependency

Current reliance on imported fossil fuels.

2%
☀️
Renewable Energy

Current grid integration.

23%
💧
Tina Hydro Status

Construction progress (Target 2028).

Project Timeline
May 2023 Project Conception

Solomon Islands seeks Australia’s support through DCCEEW.

Oct 2023 First Planning Visit

Consultations with 25+ stakeholders & Inception Workshop.

Jan 2024 Feasibility Study

Completed energy needs & RE potential assessment.

Jun 2024 Detailed Design

RE system engineering & integration planning completed.

Dec 2024 Implementation Start

Initial RE installations & grid connection.

Jul 2025 Monitoring & Evaluation

Performance review & RE expansion planning.

Key Achievements to Date

👥

Stakeholder Engagement

Consulted 25+ entities across government & private sector.

📊

Comprehensive Analysis

Identified critical barriers & opportunities for RE integration.

Pilot RE Projects

Installed demonstration solar systems in key communities.

📑

Policy Development

Drafted energy transition policy & regulatory guidelines.